Oil&Gas: Skuld Field on fast track

Statoil and its partners have submitted a plan for development and operation (PDO) of the Skuld field on the Halten Bank to the authorities.

Recoverable reserves in Skuld are estimated at 90 million barrels of oil equivalents, mostly oil. Total investments are estimated at nearly NOK 10 billion.

 

Halfdan Knudsen, who is responsible for fast-track field developments in Statoil, says that good cooperation with the partners and the authorities has ensured a fast decision process and early delivery of equipment:

 

"We have worked closely throughout the value chain from exploration, field development, drilling and wells and petroleum technology to operations, as well as experience from previous developments in the Norne area."

 

"According to the work plan, Skuld could be in production as early as the end of 2012. This would be around 2.5 years from when Dompap and Fossekall (the original names) were discovered until production starts. In other words, this can truly be called a fast-track development," says Knudsen.

 

The main Norne field was discovered in 1992 and production started in 1997. Several satellites have subsequently been tied in, and the Urd and Alve fields have been phased in to the ship for processing.

 

"The original plan was for Norne to produce until 2016, but high recovery rates and new discoveries have contributed to extending the lifetime to 2021. New field phase-ins will mean good utilisation of available capacity on the Norne production ship. This will further extend the lifetime and, in turn, lead to new exploration activity and further development in the Norne area. Now we are planning for Norne 2030," says Norne operations vice president Anita A. Stenhaug.

 

 

 

This development brings the number of Statoil fast-track PDOs to five, with Skuld the largest fast-track development so far. The plan is to have all five in operation in late 2012/early 2013. In total, the fast-track developments are expected to produce nearly 90,000 barrels per day in 2014. Skuld will contribute more than half of this volume.

Related news

Latest news

BP Awards Schlumberger Contract for Mad Dog 2 Project

Export Conference 2017: A changing world

Register for this year’s most important conference for Norwegian exporters. We can promise you an interesting and inspirational day!

Meet Elkem Silicon Materials at the Ceramics Expo 2017

Elkem Silicon Metrials invites to meet their team at the Ceramics Expo 2017. This is North America’s largest, free-to-attend exhibition for Ceramic manufacturing and applications.

Event - TechnipFMC at Gastech April 4

Most ship owners are now looking very closely at the benefits that digitalization can bring in operational gains.

Deepocean Awarded Surf Contract from BP for the Foinaven Field

DeepOcean today announced that it had received a call-off under its new Master Service Agreement (MSA) with BP Exploration Operating Company Ltd.

Parquet Floor - a Furniture in itself

Read how a Nordic style, maintenance free new floor is a furniture all in itself. 

Haavik in as Sales Director

Tor Henrik Haavik enters the role as Sales Director in Steinsvik AS. Haavik has an engineering education from Høgskolen i Haugesund and has been employed in Steinsvik since 2002. Haavik comes from the position of Sales Man...

Powder Characterization Experts Offer Solutions to Optimize Process Performance

Freeman Technology, the powder characterization specialists, will be exhibiting at the Ceramics Expo for the first time (25 – 27 April, Cleveland, OH, USA). The company offers material characterization solutions aimed at o...