Oil&Gas: Production start-up at Goliat postponed

By agreement with the partners in the Goliat licence, and due to the delay in the delivery of the production platform, Eni Norge has decided to postpone production start-up at the Goliat field until the third quarter of 2014.

When the Plan for development and operation (PDO) was submitted, the estimated start-up of the Goliat field was set to Q4 2013.

Most key project areas are progressing as planned. However, the development of the production platform facility has met challenges and increased complexity. These are mainly associated with technological innovations of the production facility.

Based on agreement in the Goliat licence the scheduled departure from the Hyundai Heavy Industries’ yard is postponed to end 2013/Q1 2014.

The progress of the other main activities for the development of Goliat will be maintained despite the delay of the production facility.

The expected cost increase, due to the postponing of the production start-up, is estimated to ca 2,5 billion NOK as a result of the delay.

Eni Norge has previously informed the Ministry of Petroleum and Energy of an increase of  investment cost of ca 3,7 billion NOK. This is mainly linked to an increase in marked prices, longer delivery time for several equipment packages and increased process for raw materials due to heavy pressure in the supplier industry.

The investment cost for the Goliat development is now estimated to ca 36,7 billion NOK. The original development cost was estimated to 30,5 billion 2012 NOK.

Goliat will be the first oil field to come into production in the Barents Sea. Eni Norge is the operator of the field (65 %) with Statoil as its partner (35 %). According to plan, Goliat will produce 170 million barrels of oil over a period of 15 years.

The Goliat field development is based on large turnkey contracts (EPC) for the supply of subsea production systems, flowlines and risers, production facility, power cable to shore, modification of the power grid in the Hammerfest area and a state of the art offshore production facility, including the use of innovative technologies.

Related news

Latest news

New contract: Windcat 41 - no 17 in the Servogear series

Servogear announces the signing of a new contract with Windcat Workboats BV for the delivery of Servogear Controllable Pitch Propellers (CPP)  for their new vessel Windcat 41. 

Seacat Enterprise to be launched January 12th

Seacat Services, is preparing to launch its first High Speed Utility Vessel (HSUV), Seacat Enterprise at January 12th.

Norsafe Signs Contract with the Swedish Coast Guard (KBV)

On Wednesday 21st December, Norsafe signed yet another new contract with the Swedish Coast Guard (KBV) to deliver nine new Magnum 750 MKII boats.

A Unique Second-generation Tomograph is Developed

A new gamma-ray tomograph designed to image up to 4” diameter pipes, is developed by CMR Prototech for the Saskatchewan Research Council (SRC) in Canada.

Sohome launches a new website

Sohome has launched a new website that makes it easier to find key information. 

Sohome AS receives orders for Johan Sverdrup Project

Sohome AS is proud to be a sub-contractor to Intelecom AS for the Johan Sverdrup Project. 

New 55'' Ultra High Definition Chart and Planning table passes Type Approval testing

Most advanced maritime display system ever produced, the 55'' Ultra High Definition Chart & Planning table, enables Integrated Bridge System manufacturers to develop new multi-data solutions.

Norsafe's experience in the Polar Code Pays Off

In readiness for the introduction of the Polar code, Norsafe has become the first LSA supplier to have executed full scale tests and trials 

Øglænd System Group winner of Business of the Year Award

Øglænd System Group won the Business of the Year Award in the Stavanger-region 2016.