National Power Transmission Grid, Mozambique

The purpose of the project is to reinforce and extend the Mozambican national power transmission grid specifically in Maputo, Gaza, Inhambane, Zambeze and Nampula Provinces.


The project includes:

  • 275kV Transmission Line Ressano Garcia – Macia (143km); including modifications to Ressano Garcia substation and new 275/110 kV Macia substation with 1x250MVA, 275/110/33 kV transformer.
  • 110kV transmission line Lindela – Massinga (110km), modifications to Lindela substation; new 110/33kV Massinga substation with a 16MVA 110/33kV transformer; 33kV line Massinga-Maxixe (70km).
  • Rural electrification in Homoine and Morumbene districts (46km 33kV line and LV network).
  • Extension of Maputo substation – installation of 1x400MVA, 400/275kV  transformer & associated equipment.
  • Reinforcement of 4 substations [(Chimuara 1x16MVA & 1x40MVA),(Quelimane 1x50/50/20MVA), Alto Molocue 1x100/100/33MVA), (Nampula 1x50 MVA)] in North region of Mozambique.
    • Power Supply to Beloluane Industrial Park (2x120MVA transformers & associated equipment, implemented as extension to Maputo substation).

The project was divided into two phases:

  • Phase 1 - Production of Design Report, Technical Specifications and Tender Documents including ESIA; Contract negotiations and award
  • Phase 2 - Construction Supervision and Project Management.

The project is structured in Packages: Main Package, Optional Package 1, Optional Package 2, and Optional Package 3. This allows for a stage activation of subsequent works which in turn allows a performance audit at various level before the next optional package is activated.

Services Rendered:

  • Line route survey and environmental impact assessment
  • Cost Estimates
  • Conceptual design and technical specifications
  • Tender documents, tender evaluation and contract negotiations
  • Design approval
  • Construction supervision and project management
     

Client: Electricidade de Moçambique (EdM)

Year:
 2011-2019

Associated companies:


Related news

Latest news

New contract: Windcat 41 - no 17 in the Servogear series

Servogear announces the signing of a new contract with Windcat Workboats BV for the delivery of Servogear Controllable Pitch Propellers (CPP)  for their new vessel Windcat 41. 

Seacat Enterprise to be launched January 12th

Seacat Services, is preparing to launch its first High Speed Utility Vessel (HSUV), Seacat Enterprise at January 12th.

Norsafe Signs Contract with the Swedish Coast Guard (KBV)

On Wednesday 21st December, Norsafe signed yet another new contract with the Swedish Coast Guard (KBV) to deliver nine new Magnum 750 MKII boats.

A Unique Second-generation Tomograph is Developed

A new gamma-ray tomograph designed to image up to 4” diameter pipes, is developed by CMR Prototech for the Saskatchewan Research Council (SRC) in Canada.

Sohome launches a new website

Sohome has launched a new website that makes it easier to find key information. 

Sohome AS receives orders for Johan Sverdrup Project

Sohome AS is proud to be a sub-contractor to Intelecom AS for the Johan Sverdrup Project. 

New 55'' Ultra High Definition Chart and Planning table passes Type Approval testing

Most advanced maritime display system ever produced, the 55'' Ultra High Definition Chart & Planning table, enables Integrated Bridge System manufacturers to develop new multi-data solutions.

Norsafe's experience in the Polar Code Pays Off

In readiness for the introduction of the Polar code, Norsafe has become the first LSA supplier to have executed full scale tests and trials 

Øglænd System Group winner of Business of the Year Award

Øglænd System Group won the Business of the Year Award in the Stavanger-region 2016.